engineers.
1.1.3 Dates ,Test, Periods and Completion
1.1.3.1 “Base Date” means the date 28 days prior to the latest date
for submission of the Tender.
1.1.3.2 “Commencement Date” means the date notified under
1.1.3.3
1.1.3.4
1.1.3.5
1.1.3.6
1.1.3.7 Sub-Clause 8.1 [Commencement of Works], unless otherwise defined in the Contract Agreement. “Time for Completion” means the time for completing the Works or a Section (as the case may be) under Sub-Clause 8.2 [Time for Completion], as stated in the Particular Conditions (with any extension under Sub-Clause 8.4 [Execution of Time for Completion]), calculated from the Commencement Date. “Tests on Completion” means the tests which are specified in the Contract or agreed by both Parties or instructed as a Variation, and which are carried out under Clause 9 [Tests on Completion] before the works or a Section (as the case may be) are taken over by the Employer. “Taking-Over Certificate” means a certificate issued under Clause 10 [Employer’s Taking Over]. “Tests after Completion” means the tests (if any) are specified in the Contract and which are carried out under Clause 12 [Tests after Completion] after the works or a Section (as the case may be) are taken over by the Employer. “Defects Notification Period” means the period for notifying
defects in the Works or a Section (as the case may be) under
Sub-Clause 11.1 [Completion of Understanding Works and
Remedying Defects], as stated in the Particular Conditions
(with any extension under Sub-Clause 11.3 [Extension of
Defects Notification Period]), calculated from the date on
which the Works or Section is competed as certified under
Sub-Clause 10.1 [Taking Over of the Works and Sections]. If
no such period is stated in the Particular Conditions, the period
shall be one year.